ANALYSIS OF PREVENTIVE MAINTENANCE ON A 6 MW HORIZONTAL-TYPE FRANCIS TURBINE USING THE MEAN TIME BETWEEN FAILURE (MTBF) AND MEAN TIME TO REPAIR (MTTR) METHODS AT THE PAKKAT HYDROPOWER PLANT OF PT ENERGY SAKTI SENTOSA
Keywords:
Francis turbine, Preventive maintenance, MTBF, MTTR, Availability, ReliabilityAbstract
The reliability of a turbine is a crucial factor in ensuring the continuous operation of a hydropower plant. This study aims to analyze the effectiveness of preventive maintenance on a 6 MW horizontal Francis turbine at Pakkat Hydropower Plant, PT. Energi Sakti Sentosa, using the Mean Time Between Failure (MTBF) and Mean Time To Repair (MTTR) methods. A quantitative approach was employed using historical turbine operation and maintenance data collected from May 2025 to May 2026. The data were obtained through field observations, interviews, documentation, and literature review. The analysis was conducted by calculating MTBF, MTTR, and availability as indicators of equipment reliability and maintenance performance. The results show that the turbine achieved an MTBF value of 558.19 hours, an MTTR value of 2.30 hours, and an availability of 92.24%. Based on the MTBF value, the recommended preventive maintenance interval is 446.55 operating hours, equivalent to approximately 18–19 days of continuous operation. These findings indicate that the existing preventive maintenance program has provided a satisfactory level of reliability. However, further improvement can be achieved by optimizing maintenance scheduling, performing regular condition monitoring of critical components, and implementing a condition-based maintenance approach to enhance equipment availability and reduce unplanned downtime.
References
Afiva, W. H., Atmaji, F. T. D., & Alhilman, J. (2019). Penerapan metode reliability centered maintenance (RCM) pada perencanaan interval preventive maintenance dan estimasi biaya pemeliharaan menggunakan analisis FMECA (Studi kasus: PT. XYZ). Jurnal PASTI, 13(3), 298–310. https://doi.org/10.22441/pasti.2019.v13i3.007
Assauri, S. (2008). Manajemen produksi dan operasi (Edisi revisi). Lembaga Penerbit Fakultas Ekonomi Universitas Indonesia.
Bancin, E. M. (2020). Analisa kinerja turbin Francis dengan turbin Archimedes screw di PLTMH Kombih Kabupaten Pakpak Bharat [Undergraduate thesis, Universitas Medan Area]. Repositori Universitas Medan Area. https://repositori.uma.ac.id/handle/123456789/15688
Fahri, F., Harahap, B., & Suliawati, S. (2025). Analisis efektivitas preventive maintenance dengan metode periodic inspection untuk meningkatkan kinerja pada unit WA800-3. Blend Sains Jurnal Teknik, 3(3), 246–267. https://doi.org/10.56211/blendsains.v3i3.799
Fatma, N. F., Ponda, H., & Kuswara, R. A. (2020). Analisis preventive maintenance dengan metode menghitung mean time between failure (MTBF) dan mean time to repair (MTTR) (Studi kasus PT. Gajah Tunggal Tbk). Heuristic, 17(2), 87–94. https://doi.org/10.30996/heuristic.v17i2.4648
Guna, G. D., & Mubarak, A. (2021). Implementasi pengembangan energi baru terbarukan pembangkit listrik tenaga mikro hidro (PLTMH) oleh Dinas Energi dan Sumber Daya Mineral Provinsi Sumatera Barat di Solok Selatan. Jurnal Manajemen dan Ilmu Administrasi Publik (JMIAP), 2(4), 28–35. https://doi.org/10.24036/jmiap.v2i4.176
Habeahan, B., Gea, H. V., & Margana, R. R. (2026). Analysis of the effectiveness of preventive maintenance implementation using mean time between failures and mean time to repair on forklift operational performance at PT XYZ. Jurnal Logic: Logistics & Supply Chain Center, 4(2), 61–66. https://doi.org/10.33197/jlscc.v4i2.3401
Haerudin, Y. H., & Wibowo, W. D. (2024). Analisis preventive maintenance mesin compressor dengan mean time beetween failure dan mean time to repair di PT Suzuki Indomobil Motor. Journal of Management and Industrial Engineering, 3(2), 73–81.
Hamsi, A. (2004). Manajemen pemeliharaan pabrik. Universitas Sumatera Utara.
Hutajulu, D. (2024). LKP Daniel Hutajulu 218130059 maintenance turbin pada pembangkit listrik tenaga air di PT. PLN Nusantara Power Unit Pelaksana Pengendalian Pembangkitan Pandan ULPLTA Sipansihaporas [Laporan kerja praktik, Universitas Medan Area]. Repositori Universitas Medan Area. https://repositori.uma.ac.id/handle/123456789/26899
Khoir, R. A. (2024). Analisis preventive maintenance pada forklift dan reach truck dengan metode menghitung mean time between failure (MTBF) dan mean time to repair (MTTR) di PT. DSV Solutions Indonesia [Undergraduate thesis, Universitas Islam Sumatera Utara]. Institutional Repository Universitas Islam Sumatera Utara. http://repository.uisu.ac.id/handle/123456789/3735
Lubis, M. M. G. (2021). LKP pemeliharaan turbin Francis pada PLTA PT. Inalum Paritohan [Laporan kerja praktik, Universitas Medan Area]. Repositori Universitas Medan Area. https://repositori.uma.ac.id/handle/123456789/19330
Marbun, L. (2025). Analisis preventive maintenance pada generator set (genset) dengan metode mean time between failure (MTBF) dan mean time to repair (MTTR) di PT. Swadaya Abdi Manunggal. INOVTEK - Seri Mesin, 2(1), 39–47.
Muhaemin, G., & Nugraha, A. E. (2022). Penerapan total productive maintenance (TPM) pada perawatan mesin cutter di PT. XYZ. Jurnal Ilmiah Wahana Pendidikan, 8(9), 205–219. https://doi.org/10.5281/zenodo.6645451
Novarika, W., Arfah, M., & Agustian, R. (2023). Analisis preventive maintenance pada mesin heater kernel dengan metode mean time between failure dan mean time to repair. Jurnal UNITEK, 16(2), 259–267. https://doi.org/10.52072/unitek.v16i2.544
Nugroho, A. (2021). Analysis of the effectiveness of dump trucks using the reliability, maintainability, and availability (RMA) method at the PT. Aneka Tambang (ANTAM) Bakau Island coal mine. MJTM: Journal of Mechanical Engineering, 4(1), 31–37.
Permatasari, C., Dasi, N. N. M. D., & Wildan, M. (2025). Analisis metode maintenance berdasarkan MTBF dan MTTR pada peralatan navigasi di Perum LPPNPI Cabang Denpasar. Jurnal Review Pendidikan dan Pengajaran, 8(1), 1078–1084. https://doi.org/10.31004/jrpp.v8i1.40701
PT Energy Sakti Sentosa. (2025). Company profile. https://www.kencanaenergy.com
Silvia, S., Suyatmo, R. I. D., & Murnianti, M. (2024). Analisis preventive maintenance berdasarkan mean time between failure (MTBF) dan mean time to repair (MTTR) pada alat blow molding di PT XYZ. Jurnal Pengabdian Masyarakat Bangsa, 2(8), 3471–3478. https://doi.org/10.59837/jpmba.v2i8.1495
Udin, D. A., & Kartawidjaja, M. A. (2025). Penerapan preventive maintenance alat berat di PT Madhani Talatah Nusantara jobsite Tanjung Enim. Jurnal Praktik Keinsinyuran, 2(5), 585–596. https://doi.org/10.25170/jpk.v2i05.6830
Wardhani, R. P. (2022). Penggunaan metode statistik Pareto chart dalam pengendalian mutu produk perusahaan. Jurnal Teknik Mesin Cakram, 5(1), 56–61. https://doi.org/10.32493/jtc.v5i1.21284
Downloads
Published
How to Cite
Issue
Section
Citation Check
License

This work is licensed under a Creative Commons Attribution 4.0 International License.
Authors submitting a manuscript do so on the understanding that if accepted for publication, the copyright of the article shall be assigned to Jurnal Dinamika Vokasional Teknik Mesin