Optimasi Biaya dan Waktu Proyek Konstruksi dengan Lembur dan Penambahan Tenaga Kerja

Dinda Fardila, Jurusan Teknik Sipil, Fakultas Teknik, Universitas Teknologi Sumbawa, NTB, 84371, Indonesia
Nuur Robbyatul Adawyah, Jurusan Teknik Sipil, Fakultas Teknik, Universitas Muhammadiyah Yogyakarta, Yogyakarta, 55183, Indonesia

Abstract


ABSTRACT                                                                        

In the construction of a construction project, there are three main elements: time efficiency, minimal costs, and appropriate quality. This study aims to calculate changes in the cost and time of project implementation with variations in overtime and additional workforce. Data analysis using Microsoft Project 2010 program and Time-Cost Trade-Off method. The results of this study indicate that (1) the optimum time and costs due to overtime are obtained at the project age of 235 working days with a total project cost of IDR 8,438,038,832 with a project time efficiency of 5 days (2.13%) and a project cost efficiency of IDR 3.559,695 (0.042%). (2) The optimum time and cost due to the addition of labor is the best choice with the results obtained at the project age of 226 working days with a total project cost of IDR 8,429,832,759 with a project time efficiency of 14 days (6.19%) and cost-efficiency. project amounting to Rp. 11,779,674 (0.14%).

 

ABSTRAK

Dalam pelaksanaan pembangunan suatu proyek konstruksi, terdapat tiga unsur utama yaitu waktu yang efisien, biaya minimal dan mutu yang sesuai. Tujuan dari penelitian ini adalah menghitung perubahan biaya dan waktu pelaksanaan proyek dengan variasi lembur dan penambahan tenaga kerja. Analisis data menggunakan program Microsoft Project 2010 dan metode Time Cost Trade Off. Hasil penelitian ini menunjukkan bahwa (1) Waktu dan biaya optimum akibat lembur didapat pada umur proyek 235 hari kerja dengan total biaya proyek sebesar Rp8.438.038.832 dengan efisiensi waktu proyek sebanyak 5 hari (2,13%) dan efisiensi biaya proyek sebesar Rp3.559.695 (0,042%). (2) Waktu dan biaya optimum akibat penambahan tenaga kerja menjadi pilihan terbaik dengan hasil yang didapat pada umur proyek 226 hari kerja dengan total biaya proyek sebesar Rp8.429.832.759 dengan efisiensi waktu proyek sebanyak 14 hari (6,19%) dan efisiensi biaya proyek sebesar Rp11.779.674 (0,14%).


Keywords


adaptive, cooperative learning, deduktif

Full Text:

PDF

References


M. R. Aulia, “Optimasi Biaya dan Waktu Proyek Konstruksi dengan Penambahan Jam Kerja dibandingkan dengan Tenaga Kerja Menggunakan Metode Time Cost Trade Off,” Universitas Muhammadiyah Yogyakarta, 2015.

I. Soeharto, Manajemen Proyek dari Konseptual Sampai Operasional. Yogyakarta: Erlangga, 1997.

G. J. Ritz, Total Construction Project Management. New York: McGrawHill, Inc, 1994.

D. A. U. Ilma, F. Fitriyanti, F. Ma’arif, N. Baldah, and B. Utoyo, “State of the art perselisihan kontrak konstruksi di Indonesia,” INERSIA, vol. 16, no. 2, pp. 158–170, 2020, doi: https://doi.org/10.21831/inersia.v16i2.36901.

A. Khalim, H. U. Ghifarsyam, N. Rozy, and F. Ma’arif, “Scheduling design of Jakarta-Cikampek II elevated toll road project (P. 186–P. 187),” J. Eng. Appl. Technol., vol. 2, no. 1, 2021, doi: https://doi.org/10.21831/jeatech.v1i2.34957.

Kementerian Tenaga Kerja dan Transmigrasi Republik Indonesia, Keputusan Menteri Tenaga Kerja dan Transmigrasi Republik Indonesia. Nomor Kep.102/Men/VI/2004 tentang Waktu Kerja Lembur dan Upah Kerja Lembur. Indonesia, 2004.

A. W. Laksana, H. S. Prasetyo, M. A. Wibowo, and A. Hidayat, “Optimalisasi waktu dan biaya proyek dengan analisa crash program,” J. Karya Tek. Sipil, vol. 3, no. 3, pp. 747–759, 2014.

N. Buluatie, “Optimalisasi Biaya dan Waktu dengan Metode Time Cost Trade Off,” Universitas Gorontalo, 2013.

A. Frederika, “Analisis percepatan pelaksanaan dengan menambah jam kerja optimum pada proyek konstruksi (Studi kasus: proyek pembangunan super villa, Peti Tenget-Badung),” J. Ilm. Tek. Sipil, vol. 14, no. 2, 2010.

W. Nuswantoro, A. B. P. Gawei, and Wiwinto, “Studi praktik estimasi biaya tidak langsung pada proyek konstruksi oleh kontraktor di kota Palangka Raya,” 2019.




DOI: https://doi.org/10.21831/inersia.v17i1.39499

Refbacks

  • There are currently no refbacks.


Copyright (c) 2022 Dinda Fardila, Nuur Robbyatul Adawyah

Creative Commons License
This work is licensed under a Creative Commons Attribution 4.0 International License.

 

Publisher:                   Co-Publisher:

Indexed by:
 
  
 

Supported by:
Jurnal Ilmiah Magister Managemen
 

Social Media:


 Online (e-ISSN): 2528-388X  || Printed (p-ISSN): 0216-762X

Lisensi Creative Commons
INERSIA by https://journal.uny.ac.id/index.php/inersia/index was distributed under a Creative Commons Attribution 4.0 International License.