PENGUASAAN METODE DIAGRAM PANAH SEBAGAI LANGKAH AWAL PEMAHAMAN TERHADAP DASAR-DASAR PENYUSUNAN NETWORK PLANNING METODA JALUR KRITIS
Abstract
In order to learn network planning, need an understanding of some of the
provisions. A project is the overall effort in the form of networks planning. The project
consists of a series of events and activity that construct a system and cycles that
boils down to an outcome. To create an operational plan, project hardware
included/required a tool that will give an idea clearly relationship, such as device is
network planning. On the operational level, the project network planning method is
the Critical Path Method (CPM). To understand the readings and analysis CPM is
necessary basics Arrow Diagramming Method. In this method will be elaborated and
relationship between activities with other activities, one event relationship with other
event system and thus forming the structure of work processes. In other words, in
the planning of the CPM, in the first of finishing is elaborated arrow diagram. Thats
mean the network planning has finish a half procces, so the next step will be easily
to finish all diagram. Network planning CPM that initially looks like very complicated
and abstract, but with an understanding of the arrow diagram will be known quickly,
which where activities having relationship that are free and which ones are
interdependent, and which part is the critical.
Keywords : Network planning, Critical path method
provisions. A project is the overall effort in the form of networks planning. The project
consists of a series of events and activity that construct a system and cycles that
boils down to an outcome. To create an operational plan, project hardware
included/required a tool that will give an idea clearly relationship, such as device is
network planning. On the operational level, the project network planning method is
the Critical Path Method (CPM). To understand the readings and analysis CPM is
necessary basics Arrow Diagramming Method. In this method will be elaborated and
relationship between activities with other activities, one event relationship with other
event system and thus forming the structure of work processes. In other words, in
the planning of the CPM, in the first of finishing is elaborated arrow diagram. Thats
mean the network planning has finish a half procces, so the next step will be easily
to finish all diagram. Network planning CPM that initially looks like very complicated
and abstract, but with an understanding of the arrow diagram will be known quickly,
which where activities having relationship that are free and which ones are
interdependent, and which part is the critical.
Keywords : Network planning, Critical path method
Full Text:
PDFDOI: https://doi.org/10.21831/inersia.v7i2.3686
Refbacks
- There are currently no refbacks.
Copyright (c) 2022 Sumardjito Sumardjito
This work is licensed under a Creative Commons Attribution 4.0 International License.
Publisher: Co-Publisher:
Indexed by:
INERSIA by https://journal.uny.ac.id/index.php/inersia/index was distributed under a Creative Commons Attribution 4.0 International License.